To make commissioning and startup as smooth as possible, Rockwell undertook an extensive Factory Acceptance Testing (FAT) period of several weeks.
“FAT is usually just a couple of days, but we wanted everything to run smoothly for Encore Tissue, so we went into meticulous detail with our testing,” said Giecco.
“As a result, the entire migration – from the start of commissioning to production – was completed in just four days, making it a highly efficient transition.”
“The steps that needed to be taken while the machine was offline were all completed within a 72-hour window from paper off to paper on, thereby achieving a successful result in a tight window.”